EV Charger Testing: A Commissioning and Maintenance Guide

How to test an EV charger: IEC 61851-1 control pilot states, RCD and DC fault protection, supply installation checks, adapter tests and maintenance.

EV Charger Testing: A Commissioning and Maintenance Guide

Electric vehicle chargers are going in at plant parking lots, distribution centers, corporate offices and delivery fleets all over Mexico. Many are commissioned with a single test: plug in a car and see if it charges. That test does not tell you whether the protective conductor is continuous, whether the residual current device trips in time, whether the charger detects a DC fault, or whether it opens its contactor when the vehicle is unplugged under load. This guide explains how the charger and the vehicle communicate, which tests are worth doing when commissioning an AC charging station, and what to check during periodic maintenance.

What an EVSE is and which standards apply

The unit mounted on the wall or on a pedestal is called EVSE (Electric Vehicle Supply Equipment). In AC charging, the actual charger is on board the vehicle; the EVSE supplies power safely, tells the vehicle how much current it may draw and disconnects if something goes wrong. The international reference standard is IEC 61851-1, which defines charging modes and the signaling system. In North America, the AC connector and signaling are described in SAE J1772, whose control signal is compatible with IEC 61851-1.

In Mexico, the installation must comply with NOM-001-SEDE, whose Article 625 deals specifically with electric vehicle charging equipment. To verify the installation feeding the charger, the principles of IEC 60364-6 and the measurement methods of IEC 61557 apply, as for any other circuit. Always check the current edition of each standard and the EVSE manufacturer’s instructions, because protection requirements vary with the model and the market it was designed for.

How the charger and the vehicle communicate

The key to safety in AC charging (mode 3) is the control pilot (CP). The EVSE generates a ±12 V signal on this wire, and the vehicle changes its level using resistors and a diode. From the positive voltage it measures, the EVSE knows which state it is in:

State CP voltage (approx.) Meaning
A +12 V Vehicle not connected
B +9 V Vehicle connected, not requesting charge
C +6 V Vehicle requesting charge
D +3 V Requesting charge, ventilation required
E 0 V Short circuit or pilot fault
F −12 V EVSE not available

When the EVSE is ready, the signal becomes a 1 kHz square wave. Its duty cycle indicates the maximum current allowed: between 10% and 85%, the current in amperes is the duty cycle multiplied by 0.6; for example, 50% means 30 A. A 5% duty cycle indicates that digital communication will be used. The EVSE must only close its contactor in states C or D and open it immediately if the signal returns to B, if the vehicle diode disappears or if earth is lost.

On Type 2 connectors (IEC 62196-2), a second contact, proximity (PP), carries a resistor that encodes the cable rating: 1.5 kΩ for 13 A, 680 Ω for 20 A, 220 Ω for 32 A and 100 Ω for 63 A. On the SAE J1772 connector, the proximity contact is used to detect that the connector is inserted and the latch released, not to encode cable current.

Testing the installation that feeds the charger

Before testing the EVSE as a device, verify the circuit that supplies it. These are the same tests as in an electrical installation verification to IEC 60364, IEC 61557 and NOM-001-SEDE, with special attention to protection against indirect contact:

  • Visual inspection: conductor size suited to the charger current and circuit length, dedicated breaker, raceway, enclosure ingress protection outdoors, mechanical protection against vehicle impact, and signage.
  • Protective conductor continuity from the panel to the EVSE earth terminal. A charger without effective earthing cannot detect faults and, on most models, should not allow charging.
  • Insulation resistance of the circuit with the EVSE disconnected, or as its manufacturer specifies, since internal electronics can be damaged or distort the reading.
  • Fault loop impedance and prospective short-circuit current, to confirm the overcurrent protection will operate within the required time.
  • Voltage, polarity and phase sequence on three-phase chargers.
  • Earth electrode resistance, if the earthing arrangement requires it.

Residual current protection and DC faults

The vehicle contains power electronics that, under an insulation fault, can produce leakage current with a DC component. A conventional Type AC residual current device, and even a Type A, can be blinded by that component and fail to trip. That is why IEC 60364-7-722 requires each connection point to have its own 30 mA RCD of at least Type A, together with a measure against DC fault currents: a Type B RCD, or a 6 mA DC detection device (RDC-DD, per IEC 62955), which many EVSEs already integrate.

Equipment designed for the North American market usually includes its own ground-fault interrupting device for the charging circuit. In every case, testing must confirm that the protection actually present works:

  • Trip test with an RCD tester: trip current and trip time, on both polarities of the waveform.
  • Smooth DC test for Type B RCDs or the EVSE’s 6 mA detection, using an instrument able to generate it.
  • Test button on the device, as an additional functional check, never as a substitute for measurement.

Functional EVSE tests with an adapter

Testing with a real vehicle only verifies the normal case. To check responses to faults you use an EV charging station test adapter, which plugs into the charger connector, simulates vehicle states and gives access to phases, neutral and earth for connecting the measuring instrument. With it you check:

  1. State A: with no vehicle, there must be no voltage on the power terminals.
  2. State B: the EVSE must generate the PWM signal with the duty cycle matching the configured current. Measure amplitude and duty cycle with an oscilloscope or the tester itself.
  3. State C: the contactor must close and nominal voltage must appear at the output. Here you measure voltage, polarity and, with the right instrument, loop impedance and RCD tripping through the charger itself.
  4. Return to B: the contactor must open within the time specified by the standard and the manufacturer.
  5. State E and missing diode: the EVSE must not energize the output.
  6. Simulated earth fault: if the adapter allows it, interrupting the protective conductor must prevent or stop charging.
  7. Real load test: a charging session with a vehicle, logging current and terminal temperature, confirms behavior under load. Thermography of the panel and EVSE during a long charge is very useful for spotting loose connections.

Periodic maintenance

A charger in an industrial parking lot is exposed to dust, moisture, impacts and cables dragged on the ground. A reasonable program includes visual inspection of the cable and connector, contact cleaning, connection tightening, an RCD trip test and a control pilot check. Frequency depends on usage, environment and manufacturer recommendations; fleet chargers with many daily sessions justify more frequent checks. Record the results to compare trends, as with any other electrical asset in the plant.

Safety during testing

Measurements on the supply circuit and at the EVSE output are made on energized parts. Apply your company’s procedures in line with NOM-029-STPS and NFPA 70E: risk assessment, suitable personal protective equipment, instruments with the correct measurement category, and lockout/tagout when the work requires it.

How we can help

At CreativeIT Group we perform EV charging system diagnostics in Monterrey, from the installation feeding the charger to the charger’s response to faults, and we rent test adapters so your maintenance team can run its own checks. See the rest of our electrical services as well. Contact us to have your charging stations checked before a fault turns into an incident.

Back to the blog

Have a project or a test coming up?

Send us the details and an engineer will get back to you today.